Tolworth Station
CASE STUDY
Robert West delivered civil engineering design services for the refurbishment of Tolworth Station, including platform resurfacing and drainage upgrades. The project required a flexible and responsive approach due to tight possession-based delivery deadlines.
To meet the programme, Robert West quickly adapted resources to align with contractor requirements and possession constraints, ensuring timely completion without compromising quality.
A key innovation was the reduction in the scope of the construction works to stabilise the platform. By adopting a reduced design-life philosophy, we aligned survey requirements accordingly—minimising on-site intrusive works while maintaining compliance with relevant standards.
This strategic approach optimised resources, reduced site disruption, and accelerated approvals. Our responsiveness and collaborative delivery ensured the design was ready ahead of critical programme milestones, contributing to the project’s overall success.